If you read “30-day deadline” in a contract, a notice or a resolution and you don’t know whether weekends count, you are facing the most common question in Chilean operational law. The answer is not unique: it depends on the law of origin. This guide organizes the rules, cites the sources and gives you a reproducible method to resolve any deadline.
1. What “day” means in a Chilean legal deadline
Calendar vs business calendar
In Chile, two ways of counting days coexist. A calendar day (día corrido) is every turn of the calendar: Monday, Tuesday, Wednesday, Thursday, Friday, Saturday, Sunday, holiday. A business day (día hábil) depends on the context: in administrative matters it is Monday to Friday excluding holidays; in judicial matters it excludes Sundays and holidays; in banking matters it also excludes December 31 and any suspension day declared by the authority.
Confusion arises because the same “15-day” deadline may end on different dates depending on which rule applies. A miscount between calendar and business days can void a defense, forfeit a right or make an appeal untimely.
Why the confusion is so common
The difference between business days and calendar days in Chile gets mixed up because contracts drafted by non-lawyers often omit the adjective. They say “30 days” without saying whether they are business or calendar days. In that scenario, the default rule is the Civil Code’s: calendar days. But if the deadline is set by a public body, it reverses: they are administrative business days.
The 10-second question: who sets the deadline?
Before counting a single day, answer:
- If the deadline is set by a State administration body: administrative business days.
- If the deadline is set by a civil court: judicial business days.
- If the deadline is set by a private contract without specifying: calendar days.
- If the deadline is set by a specific law (labor, commercial, tax): check that law.
2. The general rule: Civil Code (arts. 48 and 50)
Art. 50: deadlines are counted in full and in calendar days
Article 50 of the Civil Code sets the general rule of Chilean law: deadlines of days, months or years are understood to be full and calendar (calendar days — días corridos), unless the law or the act setting the deadline expressly states otherwise. This is the default supplementary rule: it applies when neither the law nor the agreement distinguishes.
In practical terms: if you sign a services contract that gives “15 days to cure breaches” and does not say “business”, they are 15 calendar days. Saturdays, Sundays and holidays count.
Art. 48: the “month” deadline and expiry on a non-business day
Article 48 of the Civil Code regulates how deadlines in months and years are computed. A one-month deadline expires on the same day of the following month; if that month does not have that day (for example, the 31st in February), it expires on the last day of the month. This rule applies to substantive civil deadlines, such as the statute of limitations or notice periods in leases.
The Civil Code does not provide for automatic extension if a calendar-day deadline expires on a Sunday or holiday. That extension does exist for administrative and banking deadlines, but it is not a general rule of common law.
When the general rule gives way
The rule of article 50 gives way to:
- Special law that says “business days” (for example, Law 19,880 for administrative proceedings).
- Express agreement in the contract that distinguishes “business days” or “calendar days”.
- Commercial custom recognized by law (for example, in bills of exchange and promissory notes).
If you have doubts about a specific contractual deadline, first check the literal text of the contract, then the applicable law, and only as a backup apply the Civil Code.
3. The administrative exception: Law 19,880 art. 25
Business days = Monday to Friday, excluding holidays
Article 25 of Law 19,880 on the foundations of administrative procedures reverses the general rule: in administrative proceedings, day deadlines are business days, meaning Monday to Friday, excluding holidays. This is the deadline-counting rule that applies to the entire State administration.
Law 19,880 does not only count in administrative business days: it also provides that deadlines start the day after the notice or publication of the act, and that if the last day is a non-business day, it is extended to the next business day.
What counts as an “administrative proceeding”
Any procedure before centralized or decentralized State administration bodies: ministries, public services, superintendencies, municipalities. It also applies as a supplementary rule when a special law does not set a counting rule.
Typical cases: SII, DT, municipalities, SERNAC
- SII (Internal Revenue Service): citations, assessments, administrative claims → administrative business days.
- DT (Labor Directorate): complaints, fines, defenses → administrative business days.
- Municipalities: building permits, licenses, claims → administrative business days.
- SERNAC: supplier responses to mediated claims → administrative business days.
This is the default rule for anything signed by a public officer on behalf of a State service.
Compute your exact deadline with the Chile business-day calculator — enter the start date, the number of days and get the expiry date with up-to-date holidays.4. Judicial and procedural deadlines
Code of Civil Procedure art. 66: business days by rule
Article 66 of the Code of Civil Procedure establishes that the day terms set by the CPC are deemed suspended during holidays, unless the court, with justified reasons, has expressly ordered otherwise. In practice, civil judicial deadlines are counted in judicial business days: Sundays and holidays are subtracted, but Saturday does count as a business day for counting the deadline (even though courts do not operate on Saturdays).
This is important: a “10-day” deadline in an ordinary civil trial is not the same as a “10-business-day” deadline before the SII, even though both are “business”.
February judicial recess and its effect
The February judicial recess, regulated in the Code of Courts Organization, suspends non-urgent deadlines in civil cases before ordinary courts. It does not apply to criminal, family or labor matters, which have their own enabling rules.
If your ordinary civil deadline spans February, the judicial recess days are not counted and the deadline is extended proportionally.
Criminal, family and labor matters: relevant variants
- Criminal procedure: day deadlines are calendar days, unless an express rule states otherwise. The CPP (Criminal Procedure Code) seeks speed.
- Family: deadlines are business days under the rules of Law 19,968; the judicial recess does not suspend.
- Labor: most procedural labor deadlines are business days, but some substantive deadlines (such as constructive dismissal or the final settlement) run in calendar days.
5. Matters with their own rules
Labor (Labor Code): calendar days except exceptions
The Labor Code, in substantive matters, generally uses calendar days: the 60-business-day deadline to claim unfair dismissal (art. 168) is the famous exception, but so is the 10-business-day deadline for the ratified final settlement. In labor matters it is advisable to check the specific article: do not assume calendar or business days without reading.
Commercial: bills, notes and checks — banking business days
In bills of exchange and promissory notes, payment and protest deadlines run in banking business days, which exclude Saturday, Sunday, holidays and December 31. For checks, DFL 707 of 1982 (Law on Bank Current Accounts and Checks, consolidated text) applies, with its automatic extensions if expiry falls on a non-banking day. If you are computing a promissory note expiry, check our guide to banking business days in Chile.
Tax (SII) and Treasury: administrative business days
Any citation, assessment, bill and administrative claim before the SII or General Treasury of the Republic is counted in administrative business days (Law 19,880). The only exception is deadlines before the Tax and Customs Court, which are already judicial deadlines, not administrative.
Consumer law (Law 19,496): supplier and consumer deadlines
The Consumer Protection Law sets specific deadlines (10 business days to respond to a SERNAC-mediated claim, 3 months to exercise the legal warranty), counted in administrative business days when the procedure is before SERNAC.
6. How to read a deadline in a real document
4-question checklist before counting
- Who sets the deadline? Is it a private contract, a notice from a public service, a judicial resolution or a special law?
- What word does it use? “Days”, “business days”, “calendar days”, “working days”. The adjective overrides the general rule.
- Is there an applicable special law? Labor, tax, banking, consumer. If there is, check the exact article.
- If nothing is expressed: does the Civil Code (calendar) or Law 19,880 (administrative business) apply? It depends on whether the deadline is set by a private party or by the State administration.
Summary table by area
| Area | Day type | Legal source | Notes |
|---|---|---|---|
| Civil (contracts) | Calendar | Civil Code, art. 50 | General supplementary rule |
| Administrative | Business Mon-Fri, no holidays | Law 19,880, art. 25 | All State administration |
| Civil judicial | Judicial business | CPC, art. 66 | Saturday is business, suspended in February |
| Criminal judicial | Calendar | Criminal Procedure Code | For speed |
| Labor | Mixed (check article) | Labor Code | Dismissal: 60 business; settlement: 10 business |
| Commercial (notes) | Banking business | Commercial Code, Law 18,092 | Excludes Dec 31 |
| Tax (SII) | Administrative business | Law 19,880, Tax Code | TTA is judicial |
| Consumer (SERNAC) | Administrative business | Law 19,496 | Legal warranty: 3 calendar months |
| Banking | Banking business | Law 2,977, DL 1,533 | CMF list per year |
Typical mistakes that cost dearly
- Assuming all legal deadlines are business days because the contract is “important”.
- Counting the starting day. In administrative matters, the deadline starts the day after the notice.
- Forgetting a regional or non-waivable holiday declared by the municipality.
- Not considering the February judicial recess in a civil trial.
7. Computing the deadline without error
What days are holidays in Chile in 2026
The official 2026 national holiday calendar includes the usual ones (January 1, Good Friday, May 1, May 21, June 29, July 16, August 15, September 18 and 19, October 12, November 1 and 2, December 8 and 25), plus regional and non-waivable holidays. The Chile business-day tool keeps the calendar updated by year.
Example 1: SII administrative deadline
A taxpayer receives a notice from the SII on Thursday, February 5, 2026 with a 15-day deadline to submit a defense. As it is an administrative proceeding, Law 19,880 applies: they are administrative business days (Monday to Friday, no holidays).
- Day 1: Friday, February 6, 2026.
- Days 2-6: Monday 9 to Friday 13 February.
- Days 7-11: Monday 16 to Friday 20 February.
- Days 12-15: Monday 23, Tuesday 24, Wednesday 25, Thursday 26 February.
Result: the deadline expires on Thursday, February 26, 2026.
Example 2: civil contractual deadline (lease)
A lease contract signed on Monday, March 2, 2026 gives the tenant 30 days to vacate. As the contract does not say “business”, the calendar days of article 50 of the Civil Code apply.
- Day 1: Tuesday, March 3, 2026.
- Day 30: Wednesday, April 1, 2026.
Result: the tenant must hand over the property on Wednesday, April 1, 2026. There is no extension if it falls on a non-business day, unless agreed otherwise.
Example 3: case solved with the calculator
To resolve any deadline without margin of error, use the calculator. Enter these inputs:
- Start date: 2026-01-15 (Thursday, January 15, 2026).
- Quantity: 10 business days.
- Mode: business.
- Direction: add.
Result: 2026-01-29 (Thursday, January 29, 2026).
The calculation subtracts Saturday 17, Sunday 18, Saturday 24 and Sunday 25 January, and adds only business days from Monday to Friday. You can replicate the exercise with your own dates in the Chile business-day calculator.
How to know if a deadline is business or calendar in your case
Apply the 3-step method:
- Identify the law of origin of the deadline (contract, law, resolution).
- Determine whether it sets “business” or “calendar”. If it says so, it is decisive.
- If it is silent, apply the general rule: Civil Code (calendar) for private parties, Law 19,880 (administrative business) for the State administration.
This method resolves 95% of cases. The remaining 5% requires reviewing specific case law, usually in sophisticated labor or commercial matters.
Open the Chile 2026 business-day calculator — enter date, quantity and mode, and get the exact expiry with up-to-date holidays.Counting deadlines correctly is not a professional luxury: it is a condition for your rights and obligations to exist on the right date. When in doubt, start by identifying who sets the deadline, check whether the law uses the adjective “business” and verify the result with a calculator that keeps the holiday calendar up to date.